Brooklyn Park Lift Station 32 Improvements

MCES Project No. 807910

Text Alert Icons Project Alert

Construction Update - October 5, 2018.  Please see Project Updates below to track project progress.

To receive project updates via email or text, sign up using the Enewsletter/SMS subscription form on the right.
 

Project Overview

Metropolitan Council Environmental Services (MCES) is making improvements to Lift Station 32, located at the corner of Mississippi Lane and Brookdale Drive in Brooklyn Park. Updates are being made to station structures and the odor control system. These updates will better ensure a safe work environment for MCES employees and may decrease noticeable odors emitted from the station. Lift station rehabilitation will begin January 2018 and is scheduled to be complete in April 2019.

Description of Work

The primary objective of the project is to replace the station’s odor control system. The project includes:

  • Setting up a temporary odor control system to remove or deactivate the current odor control system and install a new one
  • Building a new, larger structure around the new odor control system. This includes a roof which will prevent snow and ice build-up
  • Completing concrete repair to the primary lift station building
  • Adding a small section of asphalt near the new odor control structure

The project will take place on MCES property where Lift Station 32 is currently located. There are no anticipated impacts to nearby roads, local traffic, neighboring properties, or the environment. During parts of the project, neighbors may notice an increase in trucks and project equipment at the Lift Station, increased odor, and construction noise. From the river the lift station will look slightly different as the new odor control structure will be larger.

To learn more, review the Brooklyn Park Lift Station 32 Improvements Project Handout.

Project Updates

Construction Update - October 5, 2018 122 kB

Construction Update - July 27, 2018 4.9 MB

Construction Update - June 13, 2018 134 kB

Construction Update - May 10, 2018 296 kB

Construction Update - March 6, 2018 167 kB

Project Contacts

For more information about the Lift Station 32 Rehabilitation Project:

Email the project team: info@LiftStation32BrooklynPark.com

Call our project hotline: 763.317.7515

Sign up for Lift Station 32 Project Updates on the right.