Hopkins Lift Station Reconstruction

MCES Project No. 804100

Text Alert Icons Project Alert

Project Update - March 15, 2019.  See Project Updates below.

To receive project updates via email or text, sign up using the Enewsletter/SMS subscription form on the right.

 

Project Description

This lift station reconstruction project is part of the overall improvements included in the Hopkins System Improvements Project Facility Plan.

The project includes building a regional sanitary sewer lift station in the City of Hopkins. The selected lift station site is north of Oakes Park, between Lake Street and Hiawatha Avenue, approximately 600 feet west of Blake Road. This will replace the MCES lift station currently located at the northwest corner of the intersection of Blake Road. and Lake Street.

The project also includes sewer improvement work along Lake Street, between the lift station and Blake Road. A full closure of Lake Street is expected, with local access being maintained. Lake Street construction is scheduled to begin in spring 2019 and continue for approximately three months.

Construction overall began in summer 2016 and is currently anticipated to conclude with restoration activities in late summer/early fall 2019.  

Project Updates

Project Update - March 15, 2019 452 kB

Project Update - January 31, 2019 229 kB

Project Update - January 24, 2019 247 kB

Project Update - December 7, 2018 168 kB

Project Update - December 3, 2018 529 kB

Contacts

For more information, please contact:

Hotline: 612.276.3854
Email: info@MCESHopkins.com

Dan Fick, Principal Engineer
daniel.fick@metc.state.mn.us
651.602.1061 (Office)

Tim O'Donnell, Project Citizen Liaison
tim.odonnell@metc.state.mn.us
651.602.1269 (Office)
952.451.4689 (Cell)