Construction

Construction workers install bridge deck at the Cedar Lake Channel

Construction hotline

Call the 24-hour hotline for problems such as blocked access to business or residential areas, improper traffic sign placement or parking issues: 612-373-3933

For emergencies, always call 911.

For general questions or comments about Southwest LRT, contact your Community Outreach Coordinator.

Subscribe to updates

The Met Council provides information on construction activities every other Friday during the winter. Subscribe to receive construction activity updates by email or text.

LRT Construction Sequencing


DONE

Utilities

Excavation, Relocation / Installation


DONE

Site prep

Clear buildings, Establish work zones, detours

60% COMPLETE

Structures, Track, Stations

Track beds, track, buildings, roadwork, trails

2%
COMPLETE

Systems

Overhead catenary, safety & security, ticket vending
PRIOR TO REVENUE SERVICE

Testing

Safety, communications, operator training
 

Civil construction challenges


Corridor protection wall

  • Required per BNSF agreement
  • Required environmental clearance which was completed after civil construction contracting
  • Added to the civil construction contract by change order

Secant wall

  • Unforeseen soil conditions (settling during initial tunnel construction) necessitated an alternative construction method
  • Added to the civil construction contract by change order
  • These issues impact other contracts and the overall project schedule and budget

Can I have any of the materials (plants, trees, fencing, etc.) within construction sites and work zones?
No. Many of the natural materials within construction sites will be used for on-site erosion control.  Other materials may be contaminated and require the contractor to dispose per environmental regulations.

If I see an animal that needs assistance, what should I do?
As construction begins, some wildlife may be displaced. Should you come across animals that need assistance outside of construction areas and work zones, contact your city’s animal control office or one of the following resources:

Will there be freight train horns being sounded during construction?
Yes. With portions of the SWLRT construction corridor located immediately adjacent to active freight rail lines, freight trains will follow their standard operating rules when approaching a construction area. Freight trains are required to sound their horn as the train approaches a construction area that is occupied by workers or equipment adjacent to the freight line, until the front of the train has passed the construction area. This will mean additional train horn soundings during construction.

Safety is our top priority during construction. Please observe signage around construction areas and note conditions may change: Stay alert. Stay safe.