NOTICE: The Metropolitan Council Chair has determined it is not practical or prudent to conduct in-person meetings in response to the COVID-19 pandemic. Accordingly, committee members will participate in this meeting via telephone or other electronic means and the meeting will be conducted under Minnesota Statutes section 13D.021 at the date and time stated above. We encourage you to monitor the meeting remotely. If you have comments, we encourage members of the public to email us at
[email protected]. We will respond to your comments in a timely manner.
1-855-282-6330 United States Toll Free
Event Number: 146 899 6132
Participants: use passcode in meeting notice
Public Event Passcode: 1234
Action Required
- Welcome
- Minutes from July 29, 2021 Approval
- Resolution 21-ECCB-018 Approval
- Approval for Change Order 377 for the secant wall part two, resulting in the use of project contingency funds in the amount of $29,435,944.69.
- Resolution 21-ECCB-019 Approval
- Approval for Change Order 384 to add a load transfer platform at the south abutment area of the Minnetonka/Hopkins LRT Bridge, resulting in the use of project contingency funds in the amount of $613,711.72.
- Resolution 21-ECCB-020 Approval
- Approval for Change Order 385 to increase pile quantities, resulting in the use of project contingency funds in the amount of $2,387,985.00.
- Monthly Report on Change Orders
- Adjourn
Next Meeting: TBD