2012-231 |
Central Corridor Light Rail Transit (Green Line): Funding Agreement with the City of St. Paul for Traction Power Sub Station 12 (Mark Fuhrmann 651-602-1942) |
|
|
2. |
2012-232 |
Central Corridor Light Rail (Green Line): Easement Agreement with the Port Authority of the City of St. Paul for Traction Power Sub Station 12 (Mark Fuhrmann 651-602-1942) |
|
|
3. |
2012-236 SW |
Tokens: Temporary Fare Change Clarification (Ed Petrie 612-349-7624, Tom Randall 612-349-7364) |
|
|
|
|
|
|
VIII. |
INFORMATION |
|
|
1. |
|
Commuter Challenge Results (Bruce Howard 612-349-7694) |
|
|
2. |
|
Metropolitan Council Recommended Comments on MnDOT Multimodal Plan (Arlene McCarthy 651-602-1754, Amy Vennewitz 651-602-1058) |
|
|
3. |
|
Metro Area Freight Rail Presentation (Steven Elmer 651-602-1756, Dave Christianson – MnDOT) |
|
|
4. |
|
Special Counsel Report: Southwest LRT Engineering Services Consultant Contract Procurement (David Theisen 651-602-1706) |
|
|
|
|
|
|
|
BUSINESS |
|
|
Non-Consent Items – Continued |
|
|
4. |
2012-234 SW |
Southwest Light Rail Transit (Green Line Extension): Engineering Services Consultant Contract Procurement 11P173 (Mark Fuhrmann 651-602-1942) |
|
|
|
|
|
|
IX. |
ADJOURNMENT |
|
|
|
|
|
SW |
Action taken by Committee and Council the same week |
|
* |
Additional materials included for items on published agenda |
|
** |
Additional business item added following publication of agenda |
|
*** |
Backup materials available at the meeting |
|
|
|
|
|
|
|
|