NOTICE: The Metropolitan Council Chair has determined it is not practical or prudent to conduct in-person meetings in response to the COVID-19 pandemic. Accordingly, committee members will participate in this meeting via telephone or interactive technology and the meeting will be conducted under Minnesota Statutes section 13D.021 at the date and time stated above. We encourage you to monitor the meeting remotely. If you have comments, we encourage members of the public to email us at [email protected]. We will respond to your comments in a timely manner.

Conference call information:
1-855-282-6330 United States Toll Free
Event Number: 2498 720 1728
Participants: use passcode in meeting notice
Public Event Passcode: 1234

Agenda

 
                                                                                                                              Action Required

 
  1. Welcome
  2. Minutes from December 10, 2021                                                                Approval
  3. Resolution 22-ECCB-001                                                                             Approval
    • Approval for Change Order 0454 to the Civil Construction Contract for an increase in the allowance for unforeseen conditions, resulting in the use of project contingency funds in the amount of $1,477,000.
  4. Resolution 22-ECCB-002                                                                             Approval
    • Approval for Change Order 0455 to the Civil Construction Contract for an increase in the allowance for freight rail maintenance activities, resulting in the use of project contingency funds in the amount of $855,000.
  5. Resolution 22-ECCB-003                                                                             Approval
    • Approval of the use of contingency funds in the amount of $210,000,000 to negotiate and execute a Settlement Agreement with Lunda McCrossan JV.
  6. Resolution 22-ECCB-004                                                                             Approval
    • Approval for Change Order 034 to the Systems Construction Contract for revised conductor size requiring larger cabling, resulting in the use of project contingency funds in the amount of $460,113.18.
  7. Resolution 22-ECCB-005                                                                             Approval
    • Approval for Change Order 035 to the Systems Construction Contract for escalation costs for OCS poles, resulting in the use of project contingency funds in the amount of $418,837.12.
  8. Monthly Report on Change Orders
     
  9. Adjourn