Southwest LRT Corridor Management Committee
Wednesday, June 5th, 2013; 10:00-11:30 a.m.
St. Louis Park City Hall Council Chambers
5005 Minnetonka Boulevard St. Louis Park, MN 55416

1. Call to Order

2. Approval of May 1, 2013 Meeting Minutes

3. Legislative Update

4. FEIS Consultant Contract Award

5. Project Development Technical Issues
  • Technical Issue #1 – Eden Prairie Alignment
  • Technical Issue #2 – 9-Mile Creek Crossing
  • Technical Issue #3 – Golden Triangle Station
  • Technical Issue #4 – Shady Oak Road Crossing
  • Technical Issue #5 – City West Station
  • Technical Issue #11 – Excelsior Blvd. Crossing
  • Technical Issue #12 – Blake Station
  • Technical Issue #19 – Bassett Creek Valley Corridor: Penn Station and Van White Station
  • Technical Issue #20 – Royalston Station and The Interchange Project

6. Communications and Outreach Update
  • BAC Report
  • CAC Report

7. Adjournment

Next Meeting - Wednesday, June 12, 2013 – 1:00-2:30pm