Mound Sanitary Sewer Replacement Project

ES Project No. 819022

Text Alert Icons Project Alert

Project Update - May 2, 2024: Open House May 13, 2024 (PDF).  See previous Project Updates below.

To receive project updates via email or text, sign up using the E-newsletter/SMS subscription form on the right.

 

Project overview

Metropolitan Council Environmental Services (ES), operator of the metro-area wastewater collection and treatment system, is rehabilitating aging and deteriorating sanitary sewer pipes (called interceptors) in the cities of Mound and Spring Park starting in spring 2024. These improvements will rehabilitate infrastructure, provide capacity for future growth and increase reliability.

The replacement work will occur along Shoreline Drive. Construction is expected to begin in June 2024 and is anticipated to be completed by April 2025.

The Met Council is committed to supporting clean water and a healthy environment, and maintaining regional sewers is an important part of doing so. This project will replace the aging and deteriorating sanitary sewer to ensure ongoing service.

These sewer pipes connect community lines serving homes and businesses in Mound to the regional wastewater system. A routine inspection showed these pipes are in very poor condition and in need of immediate repair. Replacing them will improve the wastewater system and protect against breaks or leaks that could impact public and environmental health near Lake Minnetonka.

May 13 open house

An in-person open house will be held Monday, May 13, from 5:00 to 7:00 p.m. at Mound City Hall (2415 Wilshire Boulevard) in the council chambers. At the event, Met Council staff will share information about the project and anticipated construction impacts, such as road closures and detours. The project team will give a short presentation at 6:00 p.m. Staff will be available to discuss questions and concerns before and after the presentation.
 

Construction locations and activities

Project area map marked with two project sites along Shoreline Drive: one at the intersection of Auditors Road and one between Chateau Lane and West Arm Road. Construction work will focus on two main sites:
  • Shoreline Drive and Auditors Road intersection: The pipe in this area is sagging due to poor soil. A new pipe will be installed and the surrounding soil will be leveled and strengthened to prevent future issues.
  • Shoreline Drive between Chateau Lane and West Arm Road: The entire section of force main in this area will be replaced.
In 2025, Hennepin County is planning to reconstruct Shoreline Drive. Replacing the sewer pipes prior to construction will limit the overall length of disruptions in the neighborhood and prevent future construction on the newly rebuilt road.
 

Project schedule

This project is estimated to begin in June 2024 and be completed by April 2025, with final restoration in summer 2025.
 

What to expect

People who live or work near the project area may experience some disruptions.

Lane closures will be in place throughout construction, with one lane open in each direction. A full road closure and detour will be needed for several weeks during the pipe replacement at Auditors Road.

Additionally, a temporary closure and detour of the Dakota Rail Regional Trail may be necessary during portions of construction around the Seton Channel crossing.

There may be a need for excavation around some manholes to install equipment for removing existing pipes. Those living or working nearby may experience potential odors, noise and minor traffic impacts. Crews will install temporary wastewater conveyance pipes. These pipes are set up to transfer wastewater around the construction area. They will be primarily located above ground but will be buried under driveways and road crossings to maintain access. Temporary short-term closures of road and driveways will occur to bury these pipes.
 
ES will alert the community ahead of any upcoming closures or other potential disruptions. To stay up to date on the project, join the email list.
 

Aboveground temporary wastewater conveyance pipes will be installed at select locations to ensure there are no disruptions to sanitary sewer service during construction. Learn more about this in the “What is a temporary conveyance system?” section.

What is a temporary conveyance system?

Aboveground temporary wastewater conveyance pipes will be installed to ensure there are no disruptions to sewer service during construction. These pipes reroute sewer flow around the work site during construction.

Some temporary conveyance pipes may be buried under driveways or roadways to maintain access/minimize disruption. Property owners will be notified in advance if this is necessary. Diesel pumps with noise dampening equipment (low noise) will run 24 hours a day, seven days a week as part of the temporary wastewater conveyance system.

Two photos showing aboveground sewer pipes placed along a boulevard next to the roadway and temporary pipes buried below a sidewalk.

Project Updates

Open House May 13, 2024 (PDF) 531 kB

Project Map (PDF) 698 kB

Project Staff

Project Manager: Jeny Baroda, Principal Engineer, Interceptor Engineering
Council's Authorized Representatives:

  • Ron Grajczyk, Principal Contract Administrator, Construction Services
  • Cori Wallis, Contract Administrator, Constrution Services

Project Contacts

For information, please contact:

Email: [email protected]
Phone: 952-491-0074

Sign up for E-newsletter/SMS at the top right of the page.

Capital Improvement Program
Contact us

    Contact project staff with questions or concerns about this construction project.

    Email: [email protected]

    Phone: 952-491-0074