Green Line Extension Executive Change Control Board Meeting

Special Meeting
July 14, 2023 | 11:45 a.m.
Location: Green Line Extension Project Office - 6465 Wayzata Blvd., St. Louis Park, MN 55426 (5th Floor)
Minutes (PDF)


Agenda

  1. Welcome
  2. Minutes from May 12, 2023
  3. Resolution 23-ECCB-011 (PDF)
    • Approval of Change Order 44 to the Systems Contract for modification of the foundation design at 18 of the 19 substations, resulting in the use of project contingency funds in the amount of $4,524,243.46.
  4. Resolution 23-ECCB-012 (PDF)
    • Approval of Change Order 754 to the Civil Construction Contract for the Freight Crossing Replacement at 5th Avenue South in Hopkins along the east portion of the SWLRT Green Line Extension Project, resulting in the use of project contingency funds in the amount of $471,660.53.
  5. Monthly Report on Change Orders (PDF)
  6. Adjourn