District 2
Capital Program & Projects
District 2 includes, in Anoka County, the cities of Columbia Heights, Fridley, and Hilltop; in Ramsey County, the city of New Brighton; in Hennepin County, the cities of Brooklyn Park, Champlin, and Osseo; and both the Ramsey and Hennepin County portions of the city of Saint Anthony.
Capacity and condition assessments are being conducted along with regulatory reviews to identify system-wide lift station upgrades. These upgrades extend the life of facilities, reduce the risk of spills, and improve the safety of staff who operate and maintain lift stations.
This program provides funding to upgrade Environmental Services' ability to measure flows for billing, operational, and planning purposes and standardize meter equipment at similar facilities. Meter improvements include meter rehabilitation or replacement, planning meter installation, and new meter installation.
This program provides funding to address capital improvements at 8 regional wastewater treatment plants (WWTPs).
The interceptor systems in Blaine, Brooklyn Park, Champlin, Circle Pines, Coon Rapids, Forest Lake, Fridley, Hugo, Lexington, Lino Lakes, Maple Grove, Mounds View, Spring Lake Park, and other north area communities need rehabilitation and/or replacement. The project will rehabilitate existing interceptor facilities, including gravity sewers, forcemains, lift stations and meter stations.
This program includes miscellaneous projects to rehabilitate failing facilities, address Inflow and Infiltration (I/I) sources, and address general needs of the interceptor system not programmed into a region- or facility-specific program. This program also includes additional condition assessment work to complement the internal inspections work completed by operations. Office space planning and design to accommodate all the staff assigned to the Regional Maintenance Facility, and property transfer between Council and municipalities for public benefit.
This program provides funding for planning activities needed to support the Council’s overall wastewater reuse initiative.
This Program provides for the rehabilitation of concrete gravity interceptor in the cities of Champlin, Brooklyn Park, and Osseo. The interceptor will be rehabilitated using Cured-In-Place-Pipe (CIPP) technology.
This Program provides the construction of a new Lift Station 32 (L32) on the east side of the Mississippi River on Council property. This program will determine facilities which will remain on the west side of the river at the existing L32 site.
The interceptor systems in Plymouth, Maple Grove, Brooklyn Center, New Hope, Golden Valley, St. Louis Park, Medina, and other northwest area communities need rehabilitation and/or replacement as well as expansion to serve growth. The Program will rehabilitate existing interceptor facilities, including gravity sewers, forcemains, lift stations, and meter stations, and analyze the system needs to accommodate growth.
In addition to the major projects, there will be interceptor rehabilitation, lift stations, and meter improvement projects located in the district.